The beams and supports for the steeple base were attached today and work continued on purlins and horizontal members. The construction schedule calls for roofing to begin in early May and the steeple to arrive the first week of June.

Steeple support system as seen from narthex floor

Steeple connectors which come up inside the base, steeple base is larger than 8x8'

Roof purlin work

More horizontal pieces added to the high part of  the back of  the building